% Complete - doesn't seem to calculate properly, what am I missing?

I am fiddling with Project for the Web / Premium Planner in an attempt to make YouTube tutorial content. I'm creating tasks, trying to make some sample content, and setting the completed/remaining hours to be partially done to simulate an in-progress project.

 

What I'm noticing is that the %Complete tries to auto-update, but seems to be calculating really oddly? Like it's coming out with 6% complete for 1 hr completed + 1 hr remaining = 2 hr total. Am I misinterpreting what it's trying to do or is it not functioning? 

 

 

When I try to manually set the %Complete to 50% to override, it changes out the hours to be very different and it still doesn't come out right. 

 

 

 

2 Replies

  • DaveC's avatar
    DaveC
    Copper Contributor

    I'm also encountering the same problem with math errors in Planner premium.

    I can reproduce the problem by creating a new task, setting the duration to 1 day, setting the total effort to 8 hours, making the task 50% complete, and then changing the duration to 3 days. I can un-break the task by resetting the duration to 1 day, which reduces the total effort to 4.8 hours, and then resetting the total effort to 8h. Then it seems to work normally again.

    New task with duration, effort, and partially complete:

    Task after changing duration to 3 days. Completed effort and remaining effort were automatically changed.

    Task after reducing duration back to 1 day. Total effort, completed effort, and % complete were changed automatically.

    The math is now totally broken for the task. Reducing the % complete to 0, correcting the total effort to 8 hours, and increasing the % complete to 50% give a new incorrect value for completed effort.

     

  • Cat-BTB's avatar
    Cat-BTB
    Copper Contributor

    I am also experiencing a similar issue. I figured the problem on my end was that I had not properly set the effort data but after doing so (painstakingly), the percentages still are not accurate:

     